Assessment Year | 2005 |
---|---|
Principal Product | Rugs |
NAICS | 314110: Carpet and Rug Mills |
SIC | 2273: Carpets and Rugs |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
650,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 8,640
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $360,000 | 5,547,000 |
kWh
|
$0.065 |
Electricity Demand | $368,000 | 11,750 |
kW-mo/yr
|
$31.32 |
Electricity Fees | $30,000 | - |
|
- |
Natural Gas | $778,000 | 118,000 |
MMBtu
|
$6.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $279,883 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,783 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2162: Reduce excess steam bleeding | $205,920 | $22,000 | - | - |
$205,920
-
MMBtu
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $20,498 | - |
$12,152
419,040
kWh
|
$8,346
-
kW-mo/yr
|
- | |
03 | 2.4224: Upgrade controls on compressors | $7,554 | $3,000 | - |
$7,554
-
kW-mo/yr
|
- | |
04 | 2.4223: Install direct acting units in place of compressed air pressure system in safety system | $939 | $360 |
$557
19,207
kWh
|
$382
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,091 | $62,476 |
$13,689
472,046
kWh
|
$9,402
-
kW-mo/yr
|
- | |
06 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $16,309 | $15,800 | - | - |
$16,309
-
MMBtu
|
|
07 | 2.4221: Install compressor air intakes in coolest locations | $255 | $350 |
$255
8,809
kWh
|
- | - | |
08 | 2.2163: Use minimum steam operating pressure | $5,317 | - | - | - |
$5,317
-
MMBtu
|
|
TOTAL RECOMMENDED | $279,883 | $103,986 |
$26,653
919,102
kWh
|
$25,684
-
kW-mo/yr
|
$227,546
-
MMBtu
|
||
TOTAL IMPLEMENTED | $44,783 | $63,186 |
$26,653
919,102
kWh
|
$18,130
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs