ITAC Assessment: GT0797
ITAC logo
ITAC Assessment: GT0797
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Plastic and Metal Fastners
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 149
Plant Area 169,700
ft2
Annual Production 206,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $514,449 10,141,873
kWh
Natural Gas $35,099 3,821
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $165,317 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $157,107

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,893 $3,800 $1,893
66,173
kWh
- - -
02 2.4239: Eliminate or reduce compressed air usage $22,440 $1,500 $22,440
784,617
kWh
- - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $121,511 $243,073 $121,511
4,248,641
kWh
- - -
04 2.2614: Use cooling tower or economizer to replace chiller cooling $8,210 $17,150 $16,583
579,820
kWh
- $(-2,797.0) $(-5,576.0)
-
Tgal
05 2.4221: Install compressor air intakes in coolest locations $1,100 $500 $1,100
38,289
kWh
- - -
06 2.7224: Reduce space conditioning during non-working hours $7,716 $400 $6,085
212,777
kWh
$1,631
-
MMBtu
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,447 $3,692 $2,447
85,560
kWh
- - -
TOTAL RECOMMENDED $165,317 $270,115 $172,059
6,015,877
kWh
$1,631
-
MMBtu
$(-2,797.0) $(-5,576.0)
-
Tgal
TOTAL IMPLEMENTED $157,107 $252,965 $155,476
5,436,057
kWh
$1,631
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs