| Assessment Year | 2004 |
|---|---|
| Principal Product | COTTON BLENDED FABRIC |
| NAICS | 313320: Fabric Coating Mills |
| SIC | 2211: Broadwoven Fabric Mills, Cotton |
| Sales Range | n/a |
| # of Employees | 150 |
| Plant Area |
500,000
ft2
|
| Annual Production | 67,150
thousand feet
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $539,129 | 29,631,600 |
kWh
|
$0.018 |
| Electricity Demand | $437,955 | 49,944 |
kW-mo/yr
|
$8.77 |
| Electricity Fees | $14,115 | - |
|
- |
| Natural Gas | $124,212 | 22,329 |
MMBtu
|
$5.56 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $178,024 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $43,709 | - |
$21,667
940,800
kWh
|
$22,042
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $42,201 | $34,000 |
$27,972
1,214,600
kWh
|
$14,229
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.4314: Use synthetic lubricant | $30,353 | - |
$20,119
873,600
kWh
|
$10,234
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $12,828 | $48,861 |
$6,065
263,340
kWh
|
$3,085
-
kW-mo/yr
|
- | - | $3,678 | - | |
| 05 | 3.4155: Meter waste water | $7,272 | - | - | - | - | $7,272 | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,890 | $836 |
$2,580
112,056
kWh
|
$1,310
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.2135: Repair and eliminate steam leaks | $5,380 | $4,000 | - | - |
$4,270
-
MMBtu
|
- | - |
$1,110
-
Tgal
|
|
| 08 | 2.7122: Disconnect ballasts | $1,696 | $3,640 |
$1,124
48,800
kWh
|
$572
-
kW-mo/yr
|
- | - | - | - | |
| 09 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $18,125 | $6,300 | - | - |
$18,125
-
MMBtu
|
- | - | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,570 | $2,910 |
$7,850
341,163
kWh
|
$4,720
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $178,024 | $100,547 |
$87,377
3,794,359
kWh
|
$56,192
-
kW-mo/yr
|
$22,395
-
MMBtu
|
$7,272 | $3,678 |
$1,110
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs