ITAC Assessment: GT0780
ITAC logo
ITAC Assessment: GT0780
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product FROZEN DESSERTS
NAICS 311520: Ice Cream and Frozen Dessert Manufacturing
SIC 2024: Ice Cream and Frozen Desserts
Sales Range $10
M
to 50
M
# of Employees 178
Plant Area 160,000
ft2
Annual Production 8,000
Tgal
Production Hrs. Annual 2,000
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $407,759 13,175,520
kWh
Electricity Demand $389,045 47,497
kW-mo/yr
Electricity Fees $8,049 -
Natural Gas $147,842 23,434
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $107,147 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,118

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4226: Use / purchase optimum sized compressor $6,020 $11,903 $5,262
175,359
kWh
$758
-
kW-mo/yr
- - - -
02 2.1222: Install turbulators $11,482 $12,800 n/a - - $11,482
-
MMBtu
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,654 $10,261 $1,811
60,430
kWh
$2,843
-
kW-mo/yr
- - - -
04 2.2628: Utilize a less expensive cooling method $25,046 $92,125 $15,000
499,961
kWh
- - $1,420
-
Tgal
$6,954 $1,672
-
Tgal
05 2.1233: Analyze flue gas for proper air/fuel ratio $4,772 $500 - - $4,772
-
MMBtu
- - -
06 2.8112: Combine utility meters $23,320 - - - - - $23,320 -
07 2.4226: Use / purchase optimum sized compressor $1,729 $1,209 $1,729
57,638
kWh
- - - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $6,512 - $2,480
85,680
kWh
$4,032
-
kW-mo/yr
- - - -
09 2.2135: Repair and eliminate steam leaks $7,453 $900 - - $7,453
-
MMBtu
- - -
10 2.5111: Convert from indirect to direct fired systems $12,344 $20,000 - - $12,344
-
MMBtu
- - -
11 2.2437: Recover waste heat from equipment $1,325 $1,600 $1,314
43,800
kWh
$960
-
kW-mo/yr
$(-949.0)
-
MMBtu
- - -
12 2.1111: Control pressure on steamer operations $2,490 $800 - - $2,490
-
MMBtu
- - -
TOTAL RECOMMENDED $107,147 $152,098 $27,596
922,868
kWh
$8,593
-
kW-mo/yr
$37,592
-
MMBtu
$1,420
-
Tgal
$30,274 $1,672
-
Tgal
TOTAL IMPLEMENTED $27,118 $25,573 $8,802
293,427
kWh
$3,601
-
kW-mo/yr
$14,715
-
MMBtu
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs