Assessment Year | 2004 |
---|---|
Principal Product | Sausages, smoked meats |
NAICS | 311612: Meat Processed from Carcasses |
SIC | 2013: Sausages and Other Prepared Meat Products |
Sales Range | $10 M to 50M |
# of Employees | 51 |
Plant Area |
38,500
ft2
|
Annual Production | 5,500
ton
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,520 | 2,160,437 |
kWh
|
$0.045 |
Electricity Demand | $32,973 | 5,400 |
kW-mo/yr
|
$6.11 |
Natural Gas | $76,482 | 9,550 |
MMBtu
|
$8.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,368 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,959 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.5111: Convert from indirect to direct fired systems | $6,613 | $33,628 | - | - |
$6,613
-
MMBtu
|
|
02 | 2.4133: Use most efficient type of electric motors | $2,032 | $3,228 |
$452
16,268
kWh
|
$1,580
-
kW-mo/yr
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $1,134 | $100 |
$1,134
9,047
kWh
|
- | - | |
04 | 2.2511: Insulate bare equipment | $927 | $600 |
$927
20,853
kWh
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $719 | $600 |
$719
26,032
kWh
|
- | - | |
06 | 2.1111: Control pressure on steamer operations | $5,788 | $13,000 | - | - |
$5,788
-
MMBtu
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,155 | $9,815 |
$3,673
140,682
kWh
|
$4,482
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $25,368 | $60,971 |
$6,905
212,882
kWh
|
$6,062
-
kW-mo/yr
|
$12,401
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,959 | $3,828 |
$1,379
37,121
kWh
|
$1,580
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs