ITAC Assessment: GT0768
ITAC logo
ITAC Assessment: GT0768
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product VANE PUMPS
NAICS 333996: Fluid Power Pump and Motor Manufacturing
SIC 3594: Fluid Power Pumps and Motors
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area 134,000
ft2
Annual Production 150,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $284,707 12,050,760
kWh
Electricity Demand $234,876 24,180
kW-mo/yr
Natural Gas $154,739 26,842
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $117,089 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings Water Consumption Savings
01 2.4239: Eliminate or reduce compressed air usage $10,075 $15,000 n/a $10,075
224,726
kWh
- - - -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,376 - n/a - $2,040
-
kW-mo/yr
- $336 -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $42,648 - n/a - $35,700
-
kW-mo/yr
$6,948 - -
04 2.7261: Install timers and/or thermostats $13,900 $2,400 n/a $13,900
539,649
kWh
- - - -
05 2.8112: Combine utility meters $16,340 - n/a - - $16,340 - -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $17,160 - n/a - $16,816
-
kW-mo/yr
$344 - -
07 3.4111: Use closed cycle process to minimize waste water production $14,590 $4,725 n/a - - - - $14,590
-
Tgal
TOTAL RECOMMENDED $117,089 $22,125 $23,975
764,375
kWh
$54,556
-
kW-mo/yr
$23,632 $336 $14,590
-
Tgal
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs