ITAC Assessment: GT0754
ITAC logo
ITAC Assessment: GT0754
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product FABRIC DYEING
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2261: Finishers of Broadwoven Fabrics of Cotton
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 20,000,000
ft2
Annual Production 10,500,000
lb
Production Hrs. Annual 8,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $215,312 5,610,000
kWh
Electricity Demand $55,981 13,782
kW-mo/yr
Electricity Fees $15,072 -
Natural Gas $787,276 155,318
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $613,734 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $570,131

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Gas Savings Other Energy Savings Water Disposal Savings Administrative Changes Savings Water Consumption Savings
01 2.1331: Burn a less expensive grade of fuel $24,451 $69,000 - - - $24,451
-
MMBtu
- - - -
02 2.8113: Purchase gas directly from a contract gas supplier $146,600 $104,000 - - - - - - $146,600 -
03 2.1233: Analyze flue gas for proper air/fuel ratio $10,080 - - - $10,080
-
MMBtu
- - - - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $788 $1,731 $536
20,844
kWh
$252
-
kW-mo/yr
- - - - - -
05 2.2136: Install / repair insulation on steam lines $840 $678 - - - - $840
-
MMBtu
- - -
06 2.2121: Increase amount of condensate returned $87,548 $12,750 - - - - $64,821
-
MMBtu
- - $22,727
-
Tgal
07 2.2514: Cover open tanks $16,490 $6,500 - - $16,490
-
MMBtu
- - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $4,324 $2,271 $3,524
97,020
kWh
$800
-
kW-mo/yr
- - - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $2,607 $1,414 $1,974
76,800
kWh
$633
-
kW-mo/yr
- - - - - -
10 2.1113: Reduce combustion air flow to optimum $26,325 $5,750 - - $26,325
-
MMBtu
- - - - -
11 3.4115: Recover and reuse cooling water $293,681 $201,600 - - $137,927
-
MMBtu
- - $155,754
-
Tgal
- -
TOTAL RECOMMENDED $613,734 $405,694 $6,034
194,664
kWh
$1,685
-
kW-mo/yr
$190,822
-
MMBtu
$24,451
-
MMBtu
$65,661
-
MMBtu
$155,754
-
Tgal
$146,600 $22,727
-
Tgal
TOTAL IMPLEMENTED $570,131 $391,713 $5,498
173,820
kWh
$1,433
-
kW-mo/yr
$148,007
-
MMBtu
$24,451
-
MMBtu
$65,661
-
MMBtu
$155,754
-
Tgal
$146,600 $22,727
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Gas Savings Other Energy Savings Water Disposal Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs