Assessment Year | 1986 |
---|---|
Principal Product | POLYURETHANE FORA |
NAICS |
n/a
|
SIC | 2395: Pleating, Decorative and Novelty Stitching, and Tucking for the Trade |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
n/a
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $405,566 | 8,274,912 |
kWh
|
$0.049 |
Natural Gas | $54,614 | 10,880 |
MMBtu
|
$5.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,582 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,420 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $632 | $403 |
$632
12,603
kWh
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,545 | $4,500 |
$4,523
92,321
kWh
|
$(-1,978.0)
-
MMBtu
|
- | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,580 | - |
$1,580
32,239
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,037 | $500 |
$1,037
21,102
kWh
|
- | - | |
05 | 2.4312: Improve lubrication practices | $1,142 | - |
$1,307
26,671
kWh
|
- | $(-165.0) | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $287 | $450 |
$287
6,155
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $359 | $474 |
$359
7,327
kWh
|
- | - | |
TOTAL RECOMMENDED | $7,582 | $6,327 |
$9,725
198,418
kWh
|
$(-1,978.0)
-
MMBtu
|
$(-165.0) | ||
TOTAL IMPLEMENTED | $2,420 | $1,327 |
$2,585
52,756
kWh
|
- | $(-165.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs