ITAC Assessment: GT0729
ITAC logo
ITAC Assessment: GT0729
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Mining, Aggregate, Cement
NAICS
n/a
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 211
Plant Area 500,000
ft2
Annual Production 41,255
units
Production Hrs. Annual 6,420
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,566,373 61,071,551
kWh
Natural Gas $958,759 168,354
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $963,696 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.8113: Purchase gas directly from a contract gas supplier $563,200 $312,500 - - - $563,200
02 2.2442: Preheat combustion air with waste heat $74,140 $270,000 n/a - $74,140
-
MMBtu
- -
03 2.2312: Minimize non-essential material in heat treatment process $71,787 $13,892 n/a - $71,787
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,990 $1,450 $1,990
49,630
kWh
- - -
05 2.4224: Upgrade controls on compressors $60 $70 $60
1,494
kWh
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,537 $10,872 $4,537
113,416
kWh
- - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $693 $1,198 $693
17,313
kWh
- - -
08 2.4133: Use most efficient type of electric motors $12,137 $162,293 $12,137
303,434
kWh
- - -
09 2.1321: Replace fossil fuel equipment with electrical equipment $235,152 $156,000 $(-10,042.0)
(-251,053)
kWh
$245,700
-
MMBtu
$(-506.0)
-
Tgal
-
TOTAL RECOMMENDED $963,696 $928,275 $9,375
234,234
kWh
$391,627
-
MMBtu
$(-506.0)
-
Tgal
$563,200
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs