ITAC Assessment: GT0724
ITAC logo
ITAC Assessment: GT0724
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Afaghans & Tapestry Products
NAICS
n/a
SIC 2392: House furnishing, Except Curtains and Draperies
Sales Range $50
M
to 100
M
# of Employees 217
Plant Area 220,000
ft2
Annual Production 2,125,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $142,743 5,413,960
kWh
Electricity Demand $114,194 1,226
kW-mo/yr
Electricity Fees $28,549 -
Natural Gas $103,026 12,451
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $70,440 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,067

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,810 $8,370 n/a $3,281
113,004
kWh
$1,389
-
kW-mo/yr
$140 - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,554 - $1,737
59,844
kWh
$743
-
kW-mo/yr
$74 - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,832 $1,800 $4,641
159,840
kWh
$1,992
-
kW-mo/yr
$199 - -
04 2.4226: Use / purchase optimum sized compressor $4,279 $5,900 $4,154
143,087
kWh
- $125 - -
05 2.2614: Use cooling tower or economizer to replace chiller cooling $6,956 $7,500 $5,390
185,637
kWh
$1,364
-
kW-mo/yr
$202 - -
06 2.2211: Use optimum temperature $45,009 $3,850 - - - $15,009
-
MMBtu
$30,000
TOTAL RECOMMENDED $70,440 $27,420 $19,203
661,412
kWh
$5,488
-
kW-mo/yr
$740 $15,009
-
MMBtu
$30,000
TOTAL IMPLEMENTED $18,067 $15,200 $14,185
488,564
kWh
$3,356
-
kW-mo/yr
$526 - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs