Assessment Year | 2000 |
---|---|
Principal Product | Poultry |
NAICS |
n/a
|
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $50 M to 100M |
# of Employees | 420 |
Plant Area |
250,000
ft2
|
Annual Production | 27,000,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $587,649 | 9,033,119 |
kWh
|
$0.065 |
Electricity Demand | $105,464 | 19,337 |
kW-mo/yr
|
$5.45 |
Electricity Fees | $86,083 | - |
|
- |
LPG | $825,000 | 138,000 |
MMBtu
|
$5.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $352,413 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.452: Eliminate shift | $244,498 | - | n/a |
$448
9,672
kWh
|
- | - |
$28,050
-
MMBtu
|
$216,000 |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $20,694 | - | n/a |
$15,235
347,304
kWh
|
$4,284
-
kW-mo/yr
|
$1,175 | - | - |
03 | 2.2522: Isolate hot or cold equipment | $37,855 | - | n/a | - | - | - |
$37,855
-
MMBtu
|
- |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $8,198 | $1,000 | n/a | - | - | - |
$8,198
-
MMBtu
|
- |
05 | 2.2511: Insulate bare equipment | $5,763 | $3,000 | n/a | - | - | - |
$5,763
-
MMBtu
|
- |
06 | 3.4151: Minimize water usage | $680 | $600 | n/a |
$680
14,654
kWh
|
- | - | - | - |
07 | 3.4156: Use flow control valves on equipment to optimize water use | $883 | $9,000 | n/a |
$833
19,050
kWh
|
- | $50 | - | - |
08 | 3.4156: Use flow control valves on equipment to optimize water use | $505 | $900 | n/a |
$476
10,844
kWh
|
- | $29 | - | - |
09 | 2.6231: Utilize controls to operate equipment only when needed | $11,182 | $31,500 | n/a |
$421
9,086
kWh
|
- | - |
$10,761
-
MMBtu
|
- |
10 | 2.8112: Combine utility meters | $21,948 | - | n/a | - | - | $21,948 | - | - |
11 | 3.4151: Minimize water usage | $207 | $205 | n/a |
$207
4,689
kWh
|
- | - | - | - |
TOTAL RECOMMENDED | $352,413 | $46,205 |
$18,300
415,299
kWh
|
$4,284
-
kW-mo/yr
|
$23,202 |
$90,627
-
MMBtu
|
$216,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs