| Assessment Year | 2000 |
|---|---|
| Principal Product | Cotton Mats / Wool Rugs |
| NAICS |
n/a
|
| SIC | 2273: Carpets and Rugs |
| Sales Range | $5 M to 10M |
| # of Employees | 50 |
| Plant Area |
50,000
ft2
|
| Annual Production | 1,800,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $32,917 | 483,880 |
kWh
|
$0.068 |
| Electricity Demand | $7,819 | 2,553 |
kW-mo/yr
|
$3.06 |
| Electricity Fees | $6,514 | - |
|
- |
| Natural Gas | $50,969 | 6,848 |
MMBtu
|
$7.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $46,790 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $2,267 | - | n/a | - | - | - | - | - | $2,267 | - |
| 02 | 4.114: Add/modify equipment to improve drying process | $3,232 | $900 | n/a | - | - |
$742
-
MMBtu
|
- | $2,490 | - | - |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $700 | $450 | n/a | - | - |
$700
-
MMBtu
|
- | - | - | - |
| 04 | 2.4226: Use / purchase optimum sized compressor | $888 | - | n/a |
$838
-
kW-mo/yr
|
$50 | - | - | - | - | - |
| 05 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $14,296 | $28,000 | n/a | - | - |
$14,296
-
MMBtu
|
- | - | - | - |
| 06 | 3.5311: Recover and reuse waste material | $6,035 | $10,000 | n/a | - | - | - |
$6,035
-
lb
|
- | - | - |
| 07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $1,980 | $1,000 | n/a | - | - | - | - | - | - | $1,980 |
| 08 | 2.8112: Combine utility meters | $15,392 | - | n/a | - | - | - | - | - | $15,392 | - |
| 09 | 2.2511: Insulate bare equipment | $2,000 | $5,400 | n/a | - | - |
$2,000
-
MMBtu
|
- | - | - | - |
| TOTAL RECOMMENDED | $46,790 | $45,750 |
$838
-
kW-mo/yr
|
$50 |
$17,738
-
MMBtu
|
$6,035
-
lb
|
$2,490 | $17,659 | $1,980 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs