Assessment Year | 1999 |
---|---|
Principal Product | Extruded Aluminum |
NAICS |
n/a
|
SIC | 3354: Aluminum Extruded Products |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
120,000
ft2
|
Annual Production | 14,400,000
lb
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $73,730 | 5,034,291 |
kWh
|
$0.015 |
Electricity Demand | $193,542 | 1,901 |
kW-mo/yr
|
$101.81 |
Electricity Fees | $39,937 | - |
|
- |
Natural Gas | $154,319 | 40,696 |
MMBtu
|
$3.79 |
LPG | $9,653 | 1,380 |
MMBtu
|
$6.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $227,463 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,917 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4116: Meter recycled water (to reduce sewer charges) | $10,162 | - | - | - | - | - | - | - | - | - | $10,162 | - | - | |
02 | 2.1133: Adjust burners for efficient operation | $45,788 | - | - | - | - |
$48,488
-
MMBtu
|
- | - | - | $(-2,700.0) | - | - | - | |
03 | 3.5142: Treat and reuse equipment cleaning solutions | $6,800 | - | - | - | - | - | - |
$12,200
-
gal
|
- | $(-5,400.0) | - | - | - | |
04 | 3.4153: Use counter current rinsing to reduce waste water | $1,667 | $600 | - | - | - | - |
$1,667
-
Tgal
|
- | - | - | - | - | - | |
05 | 3.6192: Use a less expensive method of waste removal | $12,917 | $4,800 | - | - | - | - | - |
$12,917
-
gal
|
- | - | - | - | - | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $8,596 | $2,360 | - | - | - |
$8,596
-
MMBtu
|
- | - | - | - | - | - | - | |
07 | 2.6218: Turn off equipment when not in use | $1,970 | $1,950 |
$1,970
72,098
kWh
|
- | - | - | - | - | - | - | - | - | - | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $5,540 | $6,700 | - | - | - | - | - | - |
$5,540
-
lb
|
- | - | - | - | |
09 | 3.1162: Use less wasteful packaging | $1,024 | $3,500 | - | - | - | - | - | - | - | - | - | $1,024 | - | |
10 | 4.122: Develop standard procedures to improve internal yields | $125,800 | $64,000 | - | - | - | - | - | - | - | - | - | - | $125,800 | |
11 | 2.4133: Use most efficient type of electric motors | $4,431 | $57,365 |
$1,563
64,771
kWh
|
$2,868
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | - | |
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,768 | $6,225 |
$903
35,170
kWh
|
$1,710
-
kW-mo/yr
|
$155 | - | - | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $227,463 | $147,500 |
$4,436
172,039
kWh
|
$4,578
-
kW-mo/yr
|
$155 |
$57,084
-
MMBtu
|
$1,667
-
Tgal
|
$25,117
-
gal
|
$5,540
-
lb
|
$(-8,100.0) | $10,162 | $1,024 | $125,800 | ||
TOTAL IMPLEMENTED | $12,917 | $4,800 | - | - | - | - | - |
$12,917
-
gal
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs