Assessment Year | 2011 |
---|---|
Principal Product | Compound Plastic Bags and Laminated, Multiwall Flexible Packaging |
NAICS | 326112: Plastics Packaging Film and Sheet (including Laminated) Manufacturing |
SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
130,000
ft2
|
Annual Production | 13,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $898,877 | 9,782,370 |
kWh
|
$0.092 |
Electricity Demand | $357,186 | 21,072 |
kW-mo/yr
|
$16.95 |
Electricity Fees | $16,587 | - |
|
- |
Natural Gas | $373,515 | 56,720 |
MMBtu
|
$6.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $335,029 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $6,777 | - |
$2,103
22,880
kWh
|
- | - |
$4,674
-
MMBtu
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,056 | - |
$2,056
22,376
kWh
|
- | - | - | - | - | |
03 | 2.6218: Turn off equipment when not in use | $3,063 | $712 |
$3,063
33,331
kWh
|
- | - | - | - | - | |
04 | 2.2511: Insulate bare equipment | $6,271 | $2,850 |
$6,271
68,233
kWh
|
- | - | - | - | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $48,251 | $66,975 | - | - | - | - | $48,251 | - | |
06 | 2.7135: Install occupancy sensors | $9,933 | $14,699 |
$6,141
66,817
kWh
|
$3,792
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,404 | $22,616 |
$10,404
113,216
kWh
|
- | - | - | - | - | |
08 | 2.3212: Optimize plant power factor | $5,731 | $15,119 | - | - | $5,731 | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,700 | $41,732 |
$10,050
109,357
kWh
|
$4,231
-
kW-mo/yr
|
$105 | - | - | $1,314 | |
10 | 2.2622: Replace existing chiller with high efficiency model | $23,990 | $67,329 |
$19,152
208,400
kWh
|
$4,838
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.4239: Eliminate or reduce compressed air usage | $31,158 | $170,718 |
$31,158
339,037
kWh
|
- | - | - | - | - | |
12 | 2.9114: Use solar heat to make electricty | $171,695 | $1,807,809 |
$111,617
1,244,924
kWh
|
$60,078
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $335,029 | $2,210,559 |
$202,015
2,228,571
kWh
|
$72,939
-
kW-mo/yr
|
$5,836 |
$4,674
-
MMBtu
|
$48,251 | $1,314 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs