Assessment Year | 2000 |
---|---|
Principal Product | Recreational Vehicles |
NAICS |
n/a
|
SIC | 3799: Transportation Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 900 |
Plant Area |
365,000
ft2
|
Annual Production | 9,600
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $600,786 | 19,921,454 |
kWh
|
$0.030 |
Electricity Demand | $256,771 | 19,162 |
kW-mo/yr
|
$13.40 |
Electricity Fees | $51,450 | - |
|
- |
Natural Gas | $377,914 | 73,327 |
MMBtu
|
$5.15 |
LPG | $36,521 | 8,504 |
MMBtu
|
$4.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $112,297 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,905 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4155: Meter waste water | $4,925 | $900 | - | - | - |
$4,925
-
Tgal
|
- | - | |
02 | 2.1241: Reduce excessive boiler blowdown | $920 | $900 | - |
$920
-
MMBtu
|
- | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $4,880 | $3,500 |
$4,880
139,508
kWh
|
- | - | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,400 | - |
$5,400
154,162
kWh
|
- | - | - | - | - | |
05 | 2.4322: Use or replace with energy efficient substitutes | $8,447 | $21,000 | - |
$(-23,548.0)
-
MMBtu
|
$31,995
-
MMBtu
|
- | - | - | |
06 | 3.5142: Treat and reuse equipment cleaning solutions | $35,980 | - | - | - | - | - |
$35,980
-
gal
|
- | |
07 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $44,185 | $120,000 |
$8,317
237,691
kWh
|
$35,868
-
MMBtu
|
- | - | - | - | |
08 | 2.8112: Combine utility meters | $7,560 | $7,500 | - | - | - | - | - | $7,560 | |
TOTAL RECOMMENDED | $112,297 | $153,800 |
$18,597
531,361
kWh
|
$13,240
-
MMBtu
|
$31,995
-
MMBtu
|
$4,925
-
Tgal
|
$35,980
-
gal
|
$7,560 | ||
TOTAL IMPLEMENTED | $40,905 | $900 | - | - | - |
$4,925
-
Tgal
|
$35,980
-
gal
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs