ITAC Assessment: GT0674
ITAC logo
ITAC Assessment: GT0674
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Extruded Aluminum/Vinyl
NAICS
n/a
SIC 3354: Aluminum Extruded Products
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 142,000
ft2
Annual Production 22,200,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $222,164 7,771,395
kWh
Electricity Demand $229,397 19,091
kW-mo/yr
Electricity Fees $27,100 -
Natural Gas $276,376 59,057
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $444,380 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,348

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.8113: Purchase gas directly from a contract gas supplier $45,500 $60,000 - - - - - - - $45,500
02 2.1231: Establish burner maintenance schedule for boilers $9,592 - - - - $10,492
-
MMBtu
- - $(-900.0) -
03 2.2135: Repair and eliminate steam leaks $4,037 $400 - - - $4,037
-
MMBtu
- - - -
04 2.2121: Increase amount of condensate returned $15,646 $11,100 - - - $6,000
-
MMBtu
$9,646
-
Tgal
- - -
05 2.2514: Cover open tanks $22,910 $13,671 - - - $22,910
-
MMBtu
- - - -
06 2.4133: Use most efficient type of electric motors $1,892 $14,981 $1,083
31,946
kWh
$685
-
kW-mo/yr
$124 - - - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $419 $100 $230
7,327
kWh
$165
-
kW-mo/yr
$24 - - - - -
08 2.6231: Utilize controls to operate equipment only when needed $5,577 $2,925 $5,262
164,420
kWh
- $315 - - - - -
09 3.1191: Change procedures / equipment / operating conditions $20,189 - - - - - $11,215
-
Tgal
- $8,974 -
10 3.4151: Minimize water usage $12,618 - - - - - $7,009
-
Tgal
- $5,609 -
11 4.445: Install equipment to move product $306,000 $215,000 - - - - - $306,000 - -
TOTAL RECOMMENDED $444,380 $318,177 $6,575
203,693
kWh
$850
-
kW-mo/yr
$463 $43,439
-
MMBtu
$27,870
-
Tgal
$306,000 $13,683 $45,500
TOTAL IMPLEMENTED $6,348 $15,481 $1,313
39,273
kWh
$850
-
kW-mo/yr
$148 $4,037
-
MMBtu
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs