ITAC Assessment: GT0673
ITAC logo
ITAC Assessment: GT0673
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Printed Bags
NAICS
n/a
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $1
M
to 5
M
# of Employees 32
Plant Area 35,000
ft2
Annual Production 84,000,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,100 1,710,434
kWh
Electricity Fees $6,919 -
Natural Gas $56,440 10,403
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,507 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings Administrative Changes Savings
01 4.821: Pay bills on time to avoid late fees $6,000 - - - - $6,000
02 4.652: Replace existing equipment with more suitable substitutes $5,110 $7,000 $1,510
38,687
kWh
- - $3,600
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,422 $7,508 $2,422
58,617
kWh
- - -
04 2.2443: Re-use or recycle hot or cold process exhaust air $3,118 $5,050 - $3,118
-
MMBtu
- -
05 2.4221: Install compressor air intakes in coolest locations $410 $300 $410
10,551
kWh
- - -
06 3.8121: Cover containers to minimize evaporative losses $29,340 - - - $29,340
-
gal
-
07 3.8143: Recycle cleaning solvent and reuse $107 $320 - - $107
-
gal
-
TOTAL RECOMMENDED $46,507 $20,178 $4,342
107,855
kWh
$3,118
-
MMBtu
$29,447
-
gal
$9,600
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs