ITAC Assessment: GT0632
ITAC logo
ITAC Assessment: GT0632
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Decorative Balloons
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 310
Plant Area 176,550
ft2
Annual Production 2,000,000
lb
Production Hrs. Annual 3,315
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,298 1,432,591
kWh
Electricity Demand $49,138 5,071
kW-mo/yr
Electricity Fees $4,548 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $646,356 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $638,950

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Ancillary Material Cost Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $9,410 $37,900 $4,023
100,528
kWh
$4,855
-
kW-mo/yr
$532 - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $205 $130 $88
2,345
kWh
$105
-
kW-mo/yr
$12 - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $779 $975 $221
7,620
kWh
- $13 - $545 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $571 $3,150 $287
7,327
kWh
$256
-
kW-mo/yr
$28 - - -
05 2.7135: Install occupancy sensors $1,890 $680 $1,787
44,549
kWh
- $103 - - -
06 2.7444: Close holes and openings in building such as broken windows $740 $75 $151
3,810
kWh
$547
-
kW-mo/yr
$42 - - -
07 3.4155: Meter waste water $770 $300 - - - - $770 -
08 3.4141: Replace the chlorination stage with an oxygen or ozone stage $3,191 $15,160 $964
24,033
kWh
$849
-
kW-mo/yr
- $176
-
Tgal
$1,202 -
09 4.451: Add additional production shift $628,800 - - - - - - $628,800
TOTAL RECOMMENDED $646,356 $58,370 $7,521
190,212
kWh
$6,612
-
kW-mo/yr
$730 $176
-
Tgal
$2,517 $628,800
TOTAL IMPLEMENTED $638,950 $37,975 $4,174
104,338
kWh
$5,402
-
kW-mo/yr
$574 - - $628,800
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs