Assessment Year | 1997 |
---|---|
Principal Product | Carpet |
NAICS |
n/a
|
SIC | 2273: Carpets and Rugs |
Sales Range | $100 M to 500M |
# of Employees | 600 |
Plant Area |
750,000
ft2
|
Annual Production | 204,000
thousand feet
|
Production Hrs. Annual | 5,940
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $608,568 | 25,356,976 |
kWh
|
$0.024 |
Electricity Demand | $129,414 | 56,880 |
kW-mo/yr
|
$2.28 |
Electricity Fees | $35,785 | - |
|
- |
Natural Gas | $1,000,837 | 213,272 |
MMBtu
|
$4.69 |
Coal | $844,835 | 405,521 |
MMBtu
|
$2.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $911,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,233 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $590 | $7,976 |
$462
18,757
kWh
|
$100
-
kW-mo/yr
|
$28 | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,870 | $67,395 |
$12,545
504,103
kWh
|
$2,619
-
kW-mo/yr
|
$706 | - | - | - | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $10,030 | $17,130 |
$7,902
319,168
kWh
|
$1,650
-
kW-mo/yr
|
$478 | - | - | - | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $18,883 | $12,000 | - | - | - |
$17,992
-
MMBtu
|
- |
$891
-
Tgal
|
- | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $365,536 | $238,000 | - | - | - | - |
$(-56,290.0)
-
MMBtu
|
- | $421,826 | - | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $94,300 | $40,000 | - | - | - |
$42,600
-
MMBtu
|
- |
$51,700
-
Tgal
|
- | - | |
07 | 3.4111: Use closed cycle process to minimize waste water production | $6,643 | $4,500 | - | - | - |
$3,994
-
MMBtu
|
- |
$2,649
-
Tgal
|
- | - | |
08 | 2.2223: Enhance sensitivity of temperature control and cutoff | $23,450 | $300 | - | - | - |
$23,450
-
MMBtu
|
- | - | - | - | |
09 | 2.7111: Reduce illumination to minimum necessary levels | $10,701 | $5,100 |
$8,540
345,545
kWh
|
$1,650
-
kW-mo/yr
|
$511 | - | - | - | - | - | |
10 | 4.111: Add equipment/ operators to reduce production bottleneck | $365,300 | $800,000 | - | - | - | - | - | - | - | $365,300 | |
TOTAL RECOMMENDED | $911,303 | $1,192,401 |
$29,449
1,187,573
kWh
|
$6,019
-
kW-mo/yr
|
$1,723 |
$88,036
-
MMBtu
|
$(-56,290.0)
-
MMBtu
|
$55,240
-
Tgal
|
$421,826 | $365,300 | ||
TOTAL IMPLEMENTED | $7,233 | $12,476 |
$462
18,757
kWh
|
$100
-
kW-mo/yr
|
$28 |
$3,994
-
MMBtu
|
- |
$2,649
-
Tgal
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs