Assessment Year | 1997 |
---|---|
Principal Product | Control Panels |
NAICS |
n/a
|
SIC | 3613: Switchgear and Switchboard Apparatus |
Sales Range | $5 M to 10M |
# of Employees | 40 |
Plant Area |
28,800
ft2
|
Annual Production | 3,800,000
lb
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $26,166 | 1,046,600 |
kWh
|
$0.025 |
Electricity Demand | $55,847 | 3,728 |
kW-mo/yr
|
$14.98 |
Electricity Fees | $4,100 | - |
|
- |
Natural Gas | $8,641 | 1,344 |
MMBtu
|
$6.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $83,795 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $64,570 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $3,850 | - | - | - | - | - | - | - | - | $3,850 | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,580 | $500 |
$1,332
53,341
kWh
|
$2,198
-
kW-mo/yr
|
$2,050 | - | - | - | - | - | - | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $1,319 | $510 |
$315
12,603
kWh
|
$940
-
kW-mo/yr
|
$64 | - | - | - | - | - | - | - | - | |
04 | 2.2443: Re-use or recycle hot or cold process exhaust air | $5,510 | $15,700 |
$621
24,912
kWh
|
$3,589
-
kW-mo/yr
|
$168 |
$1,132
-
MMBtu
|
- | - | - | - | - | - | - | |
05 | 4.423: Move product using mechanical means | $13,890 | $12,000 | - | - | - | - | - |
$4,750
-
lb
|
$9,140 | - | - | - | - | |
06 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $45,100 | $8,000 | - | - | - | - | - | - | - | - | $45,100 | - | - | |
07 | 2.7261: Install timers and/or thermostats | $1,530 | $4,350 |
$1,170
46,893
kWh
|
- | $7 |
$353
-
MMBtu
|
- | - | - | - | - | - | - | |
08 | 3.5142: Treat and reuse equipment cleaning solutions | $7,016 | $10,120 | - | - | - | - |
$158
-
Tgal
|
- | - | - | - | $6,748 |
$110
-
Tgal
|
|
TOTAL RECOMMENDED | $83,795 | $51,180 |
$3,438
137,749
kWh
|
$6,727
-
kW-mo/yr
|
$2,289 |
$1,485
-
MMBtu
|
$158
-
Tgal
|
$4,750
-
lb
|
$9,140 | $3,850 | $45,100 | $6,748 |
$110
-
Tgal
|
||
TOTAL IMPLEMENTED | $64,570 | $20,500 |
$1,332
53,341
kWh
|
$2,198
-
kW-mo/yr
|
$2,050 | - | - |
$4,750
-
lb
|
$9,140 | - | $45,100 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs