ITAC Assessment: GT0484
ITAC logo
ITAC Assessment: GT0484
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product KILN-DRIED LUMBER
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 118
Plant Area
n/a
Annual Production 100,834
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $764,241 13,764,068
kWh
LPG $5,310 647
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,817 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $6,657 $206,050 $6,657
116,940
kWh
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $14,660 - $14,660
264,068
kWh
03 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $5,250 $1,400 $5,250
94,666
kWh
04 2.6232: Install set-back timers $420 $600 $420
8,792
kWh
05 2.6218: Turn off equipment when not in use $1,360 $800 $1,360
24,619
kWh
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,470 $150 $1,470
26,377
kWh
TOTAL RECOMMENDED $29,817 $209,000 $29,817
535,462
kWh
TOTAL IMPLEMENTED - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs