ITAC Assessment: GT0446
ITAC logo
ITAC Assessment: GT0446
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product STAINLESS STEEL WIRE
NAICS
n/a
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $5
M
to 10
M
# of Employees 28
Plant Area
n/a
Annual Production 2,400,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,033 1,733,587
kWh
Natural Gas $65,646 12,575
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,326 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,326

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $15,430 - $24,120
400,059
kWh
$(-8,690.0)
-
MMBtu
-
02 2.7111: Reduce illumination to minimum necessary levels $439 $140 $439
7,327
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,377 - $1,465
24,326
kWh
- $(-88.0)
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $120 $30 $120
2,052
kWh
- -
05 2.7261: Install timers and/or thermostats $18,000 $300 - $18,000
-
MMBtu
-
06 2.2136: Install / repair insulation on steam lines $80 $130 - $80
-
MMBtu
-
07 2.2514: Cover open tanks $9,880 $7,550 - $9,880
-
MMBtu
-
TOTAL RECOMMENDED $45,326 $8,150 $26,144
433,764
kWh
$19,270
-
MMBtu
$(-88.0)
TOTAL IMPLEMENTED $45,326 $8,150 $26,144
433,764
kWh
$19,270
-
MMBtu
$(-88.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs