| Assessment Year | 1991 |
|---|---|
| Principal Product | CORRUGATED PACKAGING |
| NAICS |
n/a
|
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $50 M to 100M |
| # of Employees | 190 |
| Plant Area |
n/a
|
| Annual Production | 85,800
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $467,294 | 8,508,206 |
kWh
|
$0.055 |
| Natural Gas | $54,422 | 11,078 |
MMBtu
|
$4.91 |
| LPG | $30,135 | 3,815 |
MMBtu
|
$7.90 |
| Other Energy | $5,429 | 8,088 |
MMBtu
|
$0.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $41,369 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $41,369 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Energy Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $2,647 | $11,262 |
$2,647
48,359
kWh
|
- | - | |
| 02 | 2.6232: Install set-back timers | $4,300 | - |
$4,300
140,973
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,427 | - |
$4,710
85,873
kWh
|
- | $(-283.0) | |
| 04 | 2.6232: Install set-back timers | $215 | $75 |
$215
3,810
kWh
|
- | - | |
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $13,000 | $15,000 |
$13,000
-
kWh
|
- | - | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $16,780 | - |
$16,900
307,737
kWh
|
$(-120.0)
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $41,369 | $26,337 |
$41,772
586,752
kWh
|
$(-120.0)
-
MMBtu
|
$(-283.0) | ||
| TOTAL IMPLEMENTED | $41,369 | $26,337 |
$41,772
586,752
kWh
|
$(-120.0)
-
MMBtu
|
$(-283.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Energy Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs