ITAC Assessment: MA0835
ITAC logo
ITAC Assessment: MA0835
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Baked Goods and Bread
NAICS 311811: Retail Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $50
M
to 100
M
# of Employees 135
Plant Area 125,000
ft2
Annual Production 89,271,242
lb
Production Hrs. Annual 8,760
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $662,073 9,436,623
kWh
Electricity Demand $387,920 21,966
kW-mo/yr
Electricity Fees $4,800 -
Natural Gas $680,951 80,203
MMBtu
Waste Disposal Costs
Water Usage $33,676 8,845
Tgal
Water Disposal $36,523 5,307
Tgal
TOTAL YEARLY COSTS $1,805,943
RECOMMENDED SAVINGS* $36,457 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,025

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $10,572 $40,722 - - $10,572
-
MMBtu
02 2.7234: Use heat pump for space conditioning $2,773 $7,150 $2,138
30,556
kWh
$635
-
kW-mo/yr
-
03 2.2437: Recover waste heat from equipment $18,072 $14,280 $(-2,939.0)
(-41,981)
kWh
$(-989.0)
-
kW-mo/yr
$22,000
-
MMBtu
04 2.1233: Analyze flue gas for proper air/fuel ratio $680 $750 - - $680
-
MMBtu
05 2.4231: Reduce the pressure of compressed air to the minimum required $4,360 $625 $3,248
46,401
kWh
$1,112
-
kW-mo/yr
-
TOTAL RECOMMENDED $36,457 $63,527 $2,447
34,976
kWh
$758
-
kW-mo/yr
$33,252
-
MMBtu
TOTAL IMPLEMENTED $14,025 $48,622 $2,138
30,556
kWh
$635
-
kW-mo/yr
$11,252
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs