ITAC Assessment: GT0440
ITAC logo
ITAC Assessment: GT0440
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product TOOLS AND DIES
NAICS
n/a
SIC 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds
Sales Range $5
M
to 10
M
# of Employees 125
Plant Area
n/a
Annual Production 2,565
ton
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $135,025 1,497,948
kWh
Natural Gas $11,613 1,744
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,172 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,172

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $945 $500 $945
10,551
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,354 $795 $6,354
70,633
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $7,910 $17,250 $7,910
87,925
kWh
-
04 2.2437: Recover waste heat from equipment $3,743 $2,160 - $3,743
-
MMBtu
05 2.7261: Install timers and/or thermostats $1,210 $650 - $1,210
-
MMBtu
06 2.4133: Use most efficient type of electric motors $532 $593 $532
5,862
kWh
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $898 - $898
9,965
kWh
-
08 2.8114: Change rate schedules or other changes in utility service $15,580 $70,000 $15,580
-
kWh
-
TOTAL RECOMMENDED $37,172 $91,948 $32,219
184,936
kWh
$4,953
-
MMBtu
TOTAL IMPLEMENTED $37,172 $91,948 $32,219
184,936
kWh
$4,953
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs