ITAC Assessment: GT0420
ITAC logo
ITAC Assessment: GT0420
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product TELEVISION SETS
NAICS
n/a
SIC 3651: Household Audio and Video Equipment
Sales Range $100
M
to 500
M
# of Employees 260
Plant Area
n/a
Annual Production 150,000
pieces
Production Hrs. Annual 2,496
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $260,732 4,271,981
kWh
Natural Gas $9,215 1,540
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $134,482 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,372

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.2437: Recover waste heat from equipment $2,248 $3,100 - $2,248
-
MMBtu
-
02 2.6212: Turn off equipment during breaks, reduce operating time $5,730 - $5,730
184,642
kWh
- -
03 2.6232: Install set-back timers $270 $990 $270
4,396
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $8,057 $28,321 $8,057
132,181
kWh
- -
05 2.3191: Use demand controller or load shedder $13,150 $34,000 $13,150
-
kWh
- -
06 2.4133: Use most efficient type of electric motors $377 $3,688 $377
6,155
kWh
- -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $810 - $810
13,189
kWh
- -
08 2.3191: Use demand controller or load shedder $103,840 $250,000 $111,710
-
kWh
- $(-7,870.0)
-
MMBtu
TOTAL RECOMMENDED $134,482 $320,099 $140,104
340,563
kWh
$2,248
-
MMBtu
$(-7,870.0)
-
MMBtu
TOTAL IMPLEMENTED $30,372 $69,109 $28,124
336,167
kWh
$2,248
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs