Assessment Year | 1990 |
---|---|
Principal Product | SODIUM SILICATE |
NAICS |
n/a
|
SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
Sales Range | $10 M to 50M |
# of Employees | 30 |
Plant Area |
n/a
|
Annual Production | 155,000
lb
|
Production Hrs. Annual | 7,056
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $353,238 | 7,201,055 |
kWh
|
$0.049 |
Natural Gas | $629,309 | 196,491 |
MMBtu
|
$3.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $95,849 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $408 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $94,990 | $300,000 | - |
$94,990
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $422 | $152 |
$422
8,499
kWh
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $408 | $325 |
$408
8,206
kWh
|
- | |
04 | 2.7261: Install timers and/or thermostats | $29 | $50 | - |
$29
-
MMBtu
|
|
TOTAL RECOMMENDED | $95,849 | $300,527 |
$830
16,705
kWh
|
$95,019
-
MMBtu
|
||
TOTAL IMPLEMENTED | $408 | $325 |
$408
8,206
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs