Assessment Year | 1990 |
---|---|
Principal Product | ADHESIVES & SOLID WASTES |
NAICS |
n/a
|
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $165,346 | 2,565,065 |
kWh
|
$0.064 |
Natural Gas | $96,851 | 17,818 |
MMBtu
|
$5.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,671 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,705 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $921 | $277 |
$921
14,361
kWh
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,276 | - |
$1,276
19,637
kWh
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $1,588 | $4,065 |
$1,588
24,619
kWh
|
- | |
04 | 2.1232: Keep boiler tubes clean | $1,160 | $1,000 | - |
$1,160
-
MMBtu
|
|
05 | 2.2414: Use waste heat from hot flue gases to preheat | $5,610 | $9,150 | - |
$5,610
-
MMBtu
|
|
06 | 2.2135: Repair and eliminate steam leaks | $5,760 | $275 | - |
$5,760
-
MMBtu
|
|
07 | 2.2136: Install / repair insulation on steam lines | $7,876 | $5,715 | - |
$7,876
-
MMBtu
|
|
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,730 | - |
$5,730
87,925
kWh
|
- | |
09 | 2.6232: Install set-back timers | $750 | $300 |
$750
11,723
kWh
|
- | |
TOTAL RECOMMENDED | $30,671 | $20,782 |
$10,265
158,265
kWh
|
$20,406
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,705 | $5,617 |
$3,785
58,617
kWh
|
$6,920
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs