ITAC Assessment: GT0398
ITAC logo
ITAC Assessment: GT0398
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product FROZEN MEATS
NAICS
n/a
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $10
M
to 50
M
# of Employees 375
Plant Area
n/a
Annual Production 35,000,000
lb
Production Hrs. Annual 4,400
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $791,594 15,856,976
kWh
Natural Gas $230,993 77,992
MMBtu
LPG $7,555 2,382
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $67,813 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6232: Install set-back timers $817 $400 $817
16,413
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,130 $14,910 $5,130
102,872
kWh
-
03 2.4133: Use most efficient type of electric motors $4,472 $3,777 $4,472
89,683
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $634 - $634
12,603
kWh
-
05 2.2414: Use waste heat from hot flue gases to preheat $10,294 $15,320 - $10,294
-
MMBtu
06 2.2135: Repair and eliminate steam leaks $1,275 $2,843 - $1,275
-
MMBtu
07 2.4231: Reduce the pressure of compressed air to the minimum required $201 - $201
4,103
kWh
-
08 3.4154: Eliminate leaks in water lines and valves $340 $200 - $340
-
MMBtu
09 3.4156: Use flow control valves on equipment to optimize water use $25,600 $1,500 - $25,600
-
MMBtu
10 2.2437: Recover waste heat from equipment $19,050 $76,500 - $19,050
-
MMBtu
TOTAL RECOMMENDED $67,813 $115,450 $11,254
225,674
kWh
$56,559
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs