Assessment Year | 1989 |
---|---|
Principal Product | BUILDING ADHESIVES |
NAICS |
n/a
|
SIC | 2891: Adhesives and Sealants |
Sales Range | $5 M to 10M |
# of Employees | 19 |
Plant Area |
n/a
|
Annual Production | 3,475
pieces
|
Production Hrs. Annual | 1,960
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $18,299 | 160,903 |
kWh
|
$0.11 |
Natural Gas | $39,034 | 7,185 |
MMBtu
|
$5.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,871 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,020 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $710 | - | - |
$1,010
-
MMBtu
|
$(-300.0) | |
02 | 2.2136: Install / repair insulation on steam lines | $1,021 | $895 | - |
$1,021
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $674 | $250 |
$674
5,862
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $227 | $195 |
$227
2,052
kWh
|
- | - | |
05 | 2.7141: Lower light fixtures in high ceiling areas | $1,240 | $840 |
$1,240
10,844
kWh
|
- | - | |
06 | 2.7261: Install timers and/or thermostats | $4,710 | $240 | - |
$4,710
-
MMBtu
|
- | |
07 | 2.4133: Use most efficient type of electric motors | $170 | $262 |
$170
4,689
kWh
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $119 | - |
$119
1,172
kWh
|
- | - | |
TOTAL RECOMMENDED | $8,871 | $2,682 |
$2,430
24,619
kWh
|
$6,741
-
MMBtu
|
$(-300.0) | ||
TOTAL IMPLEMENTED | $2,020 | $1,157 |
$289
5,861
kWh
|
$2,031
-
MMBtu
|
$(-300.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs