ITAC Assessment: GT0372
ITAC logo
ITAC Assessment: GT0372
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product PROTECTIVE GARMENTS
NAICS
n/a
SIC 2326: Men's and Boys' Work Clothing
Sales Range $5
M
to 10
M
# of Employees 109
Plant Area
n/a
Annual Production 2,500,000
pieces
Production Hrs. Annual 2,100
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $21,392 244,138
kWh
Natural Gas $2,604 381
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,933 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,495

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,360 $380 $2,360
26,964
kWh
02 2.4221: Install compressor air intakes in coolest locations $50 $75 $50
586
kWh
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $47 - $47
586
kWh
04 2.4133: Use most efficient type of electric motors $38 $46 $38
293
kWh
05 2.4231: Reduce the pressure of compressed air to the minimum required $438 - $438
4,982
kWh
TOTAL RECOMMENDED $2,933 $501 $2,933
33,411
kWh
TOTAL IMPLEMENTED $2,495 $501 $2,495
28,429
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs