ITAC Assessment: BD0196
ITAC logo
ITAC Assessment: BD0196
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Heavy Construction Nuts and Bolts
NAICS
n/a
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 200,000
ft2
Annual Production 35,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $280,348 11,213,920
kWh
Electricity Demand $188,527 34,277
kW-mo/yr
Electricity Fees $23,442 -
Natural Gas $345,807 50,934
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $84,893 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,323

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings One-time Revenue or Avoided Cost Savings By-product Production Savings
01 2.7231: Use radiant heater for spot heating $41,697 $18,000 - - $41,697
-
MMBtu
- - - -
02 2.4221: Install compressor air intakes in coolest locations $3,026 $2,250 $2,326
93,037
kWh
$700
-
kW-mo/yr
- - - - -
03 2.4314: Use synthetic lubricant $1,892 $900 $1,454
58,148
kWh
$438
-
kW-mo/yr
- - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,477 $200 $1,135
45,398
kWh
$342
-
kW-mo/yr
- - - - -
05 2.4133: Use most efficient type of electric motors $1,004 $3,780 $725
28,989
kWh
$279
-
kW-mo/yr
- - - - -
06 2.7135: Install occupancy sensors $984 $1,725 $583
23,323
kWh
$401
-
kW-mo/yr
- - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $754 $1,260 $502
20,077
kWh
$257
-
kW-mo/yr
- - - $(-5.0) -
08 3.3131: Use evaporation to concentrate material $19,775 $27,000 - - - $19,775
-
Tgal
- - -
09 3.5315: Lease / purchase baler; sell cardboard to recycler $5,282 $7,000 - - - - $5,282
-
lb
- -
10 3.4154: Eliminate leaks in water lines and valves $2,862 $750 - - - $2,862
-
Tgal
- - -
11 4.222: Purchase re-conditioned material instead of new $6,140 $1,000 - - - - - - $6,140
TOTAL RECOMMENDED $84,893 $63,865 $6,725
268,972
kWh
$2,417
-
kW-mo/yr
$41,697
-
MMBtu
$22,637
-
Tgal
$5,282
-
lb
$(-5.0) $6,140
TOTAL IMPLEMENTED $5,323 $2,675 $1,718
68,721
kWh
$743
-
kW-mo/yr
- $2,862
-
Tgal
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings One-time Revenue or Avoided Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs