ITAC Assessment: GT0346
ITAC logo
ITAC Assessment: GT0346
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product PUMPS & PUMP PARTS
NAICS
n/a
SIC 3561: Pumps and Pumping Equipment
Sales Range $1
M
to 5
M
# of Employees 24
Plant Area
n/a
Annual Production 475
ton
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,724 403,869
kWh
Natural Gas $8,942 1,828
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,813 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $170

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7231: Use radiant heater for spot heating $1,950 $3,600 - $1,950
-
MMBtu
02 2.4133: Use most efficient type of electric motors $170 $259 $170
2,052
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $450 - $450
4,982
kWh
-
04 3.4154: Eliminate leaks in water lines and valves $558 $20 $416
4,396
kWh
$142
-
MMBtu
05 2.7261: Install timers and/or thermostats $660 $350 - $660
-
MMBtu
06 2.7142: Utilize higher efficiency lamps and/or ballasts $105 $202 $105
1,172
kWh
-
07 2.8114: Change rate schedules or other changes in utility service $1,760 $2,640 $1,760
-
kWh
-
08 2.2511: Insulate bare equipment $160 $30 $110
1,172
kWh
$50
-
MMBtu
TOTAL RECOMMENDED $5,813 $7,101 $3,011
13,774
kWh
$2,802
-
MMBtu
TOTAL IMPLEMENTED $170 $259 $170
2,052
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs