ITAC Assessment: GT0312
ITAC logo
ITAC Assessment: GT0312
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product CARPET BACKING
NAICS
n/a
SIC 2299: Textile goods, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 23
Plant Area
n/a
Annual Production 72,000,000
lb
Production Hrs. Annual 2,060
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $77,678 1,089,977
kWh
Natural Gas $276 34
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,015 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,830

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7121: Utilize daylight whenever possible in lieu of artificial light $546 - $546
7,620
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $100 $293 $100
1,465
kWh
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,184 $3,615 $1,184
14,947
kWh
04 2.4133: Use most efficient type of electric motors $185 $1,050 $185
2,638
kWh
TOTAL RECOMMENDED $2,015 $4,958 $2,015
26,670
kWh
TOTAL IMPLEMENTED $1,830 $3,908 $1,830
24,032
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs