ITAC Assessment: BD0255
ITAC logo
ITAC Assessment: BD0255
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Industrial Coatings
NAICS 325510: Paint and Coating Manufacturing
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 60,000
ft2
Annual Production 23,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $207,689 3,738,240
kWh
Electricity Demand $82,852 8,210
kW-mo/yr
Natural Gas $71,679 11,712
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $84,303 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.4133: Use most efficient type of electric motors $16,352 $17,885 $10,814
380,765
kWh
$5,538
-
kW-mo/yr
- - - -
02 2.7495: Install replacement doors $13,961 $14,000 - - $821
-
MMBtu
$13,140 - -
03 4.111: Add equipment/ operators to reduce production bottleneck $11,914 $11,000 $8,450
297,550
kWh
$3,464
-
kW-mo/yr
- - - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,576 $13,050 $4,501
158,480
kWh
$3,075
-
kW-mo/yr
- - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $3,780 $2,000 $2,539
89,414
kWh
$1,241
-
kW-mo/yr
- - - -
06 2.7135: Install occupancy sensors $2,761 $2,550 $1,045
36,730
kWh
$1,525
-
kW-mo/yr
- $35 - $156
07 2.1213: Direct warmest air to combustion intake $2,586 $2,000 - - $2,586
-
MMBtu
- - -
08 2.4221: Install compressor air intakes in coolest locations $1,238 $750 $834
29,738
kWh
$404
-
kW-mo/yr
- - - -
09 2.2437: Recover waste heat from equipment $1,069 $1,500 - - $1,069
-
MMBtu
- - -
10 2.1222: Install turbulators $899 $1,200 - - $899
-
MMBtu
- - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $739 $995 $236
8,299
kWh
$160
-
kW-mo/yr
- $144 - $199
12 2.7135: Install occupancy sensors $570 $150 $318
11,190
kWh
$252
-
kW-mo/yr
- - - -
13 2.3131: Reschedule plant operations or reduce load to avoid peaks $12,428 $2,000 - $12,428
-
kW-mo/yr
- - - -
14 4.447: Automate payroll system $6,240 $3,000 - - - $6,240 - -
15 4.821: Pay bills on time to avoid late fees $2,190 - - - - - $2,190 -
TOTAL RECOMMENDED $84,303 $72,080 $28,737
1,012,166
kWh
$28,087
-
kW-mo/yr
$5,375
-
MMBtu
$19,559 $2,190 $355
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs