| Assessment Year | 2025 |
|---|---|
| Principal Product | Pipe Manufacturing |
| NAICS | 332996: Fabricated Pipe and Pipe Fitting Manufacturing |
| SIC | 3498: Fabricated Pipe and Pipe Fittings |
| Sales Range | $100 M to 500M |
| # of Employees | 230 |
| Plant Area |
249,000
ft2
|
| Annual Production | 50,000
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $927,961 | 10,662,580 |
kWh
|
$0.087 | |
| Electricity Demand | $373,706 | 32,727 |
kW-mo/yr
|
$11.42 | |
| Natural Gas | $13,561 | 2,100 |
MMBtu
|
$6.46 | |
| Waste Disposal Costs | |||||
| Water Usage | $3,460 | 1,000 |
Tgal
|
$3.46 | |
| Water Disposal | $10,476 | 1,000 |
Tgal
|
$10.48 | |
| TOTAL YEARLY COSTS | $1,329,163 | ||||
| RECOMMENDED SAVINGS* | $10,813 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $811 | $402 |
$647
7,441
kWh
|
$163
-
kW-mo/yr
|
|
| 02 | 2.6218: Turn off equipment when not in use | $613 | $227 |
$518
5,957
kWh
|
$94
-
kW-mo/yr
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,389 | $4,701 |
$9,389
107,925
kWh
|
- | |
| TOTAL RECOMMENDED | $10,813 | $5,331 |
$10,555
121,323
kWh
|
$258
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs