Assessment Year | 1984 |
---|---|
Principal Product | FLEXIBLE PACKAGING |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 6,000,000
lb
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $181,406 | 3,963,072 |
kWh
|
$0.046 |
Natural Gas | $76,810 | 14,600 |
MMBtu
|
$5.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,785 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,071 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $6,010 | $2,400 | - |
$6,010
-
MMBtu
|
|
02 | 2.2443: Re-use or recycle hot or cold process exhaust air | $795 | $1,000 | - |
$795
-
MMBtu
|
|
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,057 | $1,000 | - |
$1,057
-
MMBtu
|
|
04 | 2.2135: Repair and eliminate steam leaks | $575 | $50 | - |
$575
-
MMBtu
|
|
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $919 | $500 |
$919
-
kWh
|
- | |
06 | 2.4133: Use most efficient type of electric motors | $645 | $368 |
$645
14,068
kWh
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,404 | $1,270 |
$1,404
30,774
kWh
|
- | |
08 | 2.6232: Install set-back timers | $330 | - |
$330
7,327
kWh
|
- | |
09 | 2.2511: Insulate bare equipment | $50 | $150 |
$50
1,172
kWh
|
- | |
TOTAL RECOMMENDED | $11,785 | $6,738 |
$3,348
53,341
kWh
|
$8,437
-
MMBtu
|
||
TOTAL IMPLEMENTED | $10,071 | $5,238 |
$2,429
53,341
kWh
|
$7,642
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs