| Assessment Year | 1984 |
|---|---|
| Principal Product | STAINLESS STEEL PRODUCTS |
| NAICS |
n/a
|
| SIC | 3841: Surgical and Medical Instruments and Apparatus |
| Sales Range | $5 M to 10M |
| # of Employees | 61 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $24,533 | 288,980 |
kWh
|
$0.085 |
| Natural Gas | $12,807 | 2,370 |
MMBtu
|
$5.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,520 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,030 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $390 | $300 | - |
$390
-
MMBtu
|
|
| 02 | 2.7243: Improve air circulation with destratification fans / other methods | $1,340 | $2,300 |
$(-100.0)
(-2,052)
kWh
|
$1,440
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,510 | $2,350 |
$1,510
17,878
kWh
|
- | |
| 04 | 2.7122: Disconnect ballasts | $60 | $50 |
$60
586
kWh
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $70 | $149 |
$70
879
kWh
|
- | |
| 06 | 2.2711: Utilize outside air instead of conditioned air for drying | $180 | $350 | - |
$180
-
MMBtu
|
|
| 07 | 2.2532: Use only amount of air necessary to prevent explosion hazard | $1,190 | $3,000 | - |
$1,190
-
MMBtu
|
|
| 08 | 2.7492: Use proper thickness of insulation on building envelope | $1,780 | $11,625 | - |
$1,780
-
MMBtu
|
|
| TOTAL RECOMMENDED | $6,520 | $20,124 |
$1,540
17,291
kWh
|
$4,980
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $2,030 | $2,849 |
$1,640
19,343
kWh
|
$390
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs