| Assessment Year | 1982 |
|---|---|
| Principal Product | PROCESSED PORK PRODUCTS |
| NAICS |
n/a
|
| SIC | 2013: Sausages and Other Prepared Meat Products |
| Sales Range | $10 M to 50M |
| # of Employees | 176 |
| Plant Area |
n/a
|
| Annual Production | 12,000
ton
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $318,319 | 7,145,076 |
kWh
|
$0.045 |
| Natural Gas | $221,673 | 50,789 |
MMBtu
|
$4.36 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $55,884 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.5194: Redesign process | $13,575 | - |
$13,575
597,890
kWh
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $21,800 | $41,300 | - |
$21,800
-
MMBtu
|
|
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,669 | - | - |
$5,669
-
MMBtu
|
|
| 04 | 2.4133: Use most efficient type of electric motors | $2,169 | $2,789 |
$2,169
49,531
kWh
|
- | |
| 05 | 2.3191: Use demand controller or load shedder | $5,560 | $9,000 |
$5,560
-
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $345 | $120 |
$345
7,913
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $515 | $3,240 |
$515
11,723
kWh
|
- | |
| 08 | 2.2514: Cover open tanks | $324 | $100 | - |
$324
-
MMBtu
|
|
| 09 | 2.7251: Reduce air conditioning load by evaporating water from roof | $5,927 | $9,085 |
$5,927
69,461
kWh
|
- | |
| TOTAL RECOMMENDED | $55,884 | $65,634 |
$28,091
736,518
kWh
|
$27,793
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs