ITAC Assessment: GT0127
ITAC logo
ITAC Assessment: GT0127
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product PAINT BRUSHES & ROLLERS
NAICS
n/a
SIC 3991: Brooms and Brushes
Sales Range $1
M
to 5
M
# of Employees 80
Plant Area
n/a
Annual Production 237,500
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $20,296 267,585
kWh
Natural Gas $8,157 2,109
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,300 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,916

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,156 $180 $3,156
41,618
kWh
-
02 2.7261: Install timers and/or thermostats $2,466 $1,500 - $2,466
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,384 $345 $1,384
18,171
kWh
-
04 2.4133: Use most efficient type of electric motors $294 $414 $294
3,810
kWh
-
TOTAL RECOMMENDED $7,300 $2,439 $4,834
63,599
kWh
$2,466
-
MMBtu
TOTAL IMPLEMENTED $5,916 $2,094 $3,450
45,428
kWh
$2,466
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs