Assessment Year | 1982 |
---|---|
Principal Product | CORRUGATED PAPER SHEETS |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $5 M to 10M |
# of Employees | 74 |
Plant Area |
n/a
|
Annual Production | 172,000
pieces
|
Production Hrs. Annual | 1,632
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $77,652 | 1,240,914 |
kWh
|
$0.063 |
Natural Gas | $102,719 | 25,599 |
MMBtu
|
$4.01 |
Fuel Oil #2 | $14,215 | 1,915 |
MMBtu
|
$7.42 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,980 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,148 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Paper Savings |
---|---|---|---|---|---|---|---|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,452 | $564 |
$1,452
23,154
kWh
|
- | - | |
03 | 2.2135: Repair and eliminate steam leaks | $4,378 | $600 | - |
$4,378
-
MMBtu
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,770 | $250 |
$1,770
28,429
kWh
|
- | - | |
05 | 2.7261: Install timers and/or thermostats | $1,259 | $2,000 | - |
$1,259
-
MMBtu
|
- | |
06 | 3.6121: Burn waste paper for heat | $10,121 | $46,000 | - |
$44,821
-
MMBtu
|
$(-34,700.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $18,980 | $49,414 |
$3,222
51,583
kWh
|
$50,458
-
MMBtu
|
$(-34,700.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $6,148 | $850 |
$1,770
28,429
kWh
|
$4,378
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs