| Assessment Year | 1982 |
|---|---|
| Principal Product | CIRCUIT BOARDS, PARTS |
| NAICS |
n/a
|
| SIC | 3679: Electronic Components, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,732
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $105,260 | 2,137,456 |
kWh
|
$0.049 |
| Natural Gas | $45,133 | 11,376 |
MMBtu
|
$3.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,795 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $1,518 | $2,760 |
$(-12.0)
(-293)
kWh
|
$1,530
-
MMBtu
|
|
| 02 | 2.7492: Use proper thickness of insulation on building envelope | $7,669 | $5,792 |
$3,702
75,029
kWh
|
$3,967
-
MMBtu
|
|
| 03 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $7,298 | $1,500 |
$7,298
148,300
kWh
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $310 | $500 |
$310
6,155
kWh
|
- | |
| TOTAL RECOMMENDED | $16,795 | $10,552 |
$11,298
229,191
kWh
|
$5,497
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs