Assessment Year | 2000 |
---|---|
Principal Product | Printed Circuit Boards |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 185 |
Plant Area |
45,000
ft2
|
Annual Production | 2,196,400
pieces
|
Production Hrs. Annual | 6,732
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $302,087 | 6,222,743 |
kWh
|
$0.049 |
Electricity Demand | $36,880 | 15,168 |
kW-mo/yr
|
$2.43 |
Electricity Fees | $60,160 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $88,803 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,704 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,779 | $15,136 |
$7,428
142,438
kWh
|
$351
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
02 | 2.7232: Replace existing hvac unit with high efficiency model | $6,019 | $14,000 |
$5,874
116,354
kWh
|
$145
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $401 | $510 |
$239
4,396
kWh
|
$17
-
kW-mo/yr
|
- | - | $72 | - | $73 | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $176 | $158 |
$62
1,172
kWh
|
- | - | - | $98 | - | $16 | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $816 | $1,466 |
$699
12,603
kWh
|
$117
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
06 | 2.7135: Install occupancy sensors | $640 | $975 |
$611
11,430
kWh
|
$29
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
07 | 3.5217: Reuse / recycle/ sell paper products | $2,969 | $120 | - | - | - |
$1,349
-
lb
|
- | - | - | - | $1,620 | - | |
08 | 3.6192: Use a less expensive method of waste removal | $384 | $60 | - | - | - |
$384
-
lb
|
- | - | - | - | - | - | |
09 | 3.6192: Use a less expensive method of waste removal | $8,160 | $120 | - | - | - |
$8,160
-
lb
|
- | - | - | - | - | - | |
10 | 3.4156: Use flow control valves on equipment to optimize water use | $5,595 | $820 | - | - |
$5,595
-
Tgal
|
- | - | - | - | - | - | - | |
11 | 4.652: Replace existing equipment with more suitable substitutes | $54,284 | $180,000 | - | - | - | - | $48,960 | - | - | - | - | $5,324 | |
12 | 4.812: Apply for investment incentives | $1,580 | $60 | - | - | - | - | - | $1,066 | - | $514 | - | - | |
TOTAL RECOMMENDED | $88,803 | $213,425 |
$14,913
288,393
kWh
|
$659
-
kW-mo/yr
|
$5,595
-
Tgal
|
$9,893
-
lb
|
$49,130 | $1,066 | $89 | $514 | $1,620 | $5,324 | ||
TOTAL IMPLEMENTED | $26,704 | $31,570 |
$14,302
276,963
kWh
|
$630
-
kW-mo/yr
|
- |
$9,893
-
lb
|
$170 | - | $89 | - | $1,620 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs