ITAC Assessment: AS0274
ITAC logo
ITAC Assessment: AS0274
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Printed Circuit Boards
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $10
M
to 50
M
# of Employees 185
Plant Area 45,000
ft2
Annual Production 2,196,400
pieces
Production Hrs. Annual 6,732
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $302,087 6,222,743
kWh
Electricity Demand $36,880 15,168
kW-mo/yr
Electricity Fees $60,160 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $88,803 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,704

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings By-product Production Savings Increase in Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,779 $15,136 $7,428
142,438
kWh
$351
-
kW-mo/yr
- - - - - - - -
02 2.7232: Replace existing hvac unit with high efficiency model $6,019 $14,000 $5,874
116,354
kWh
$145
-
kW-mo/yr
- - - - - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $401 $510 $239
4,396
kWh
$17
-
kW-mo/yr
- - $72 - $73 - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $176 $158 $62
1,172
kWh
- - - $98 - $16 - - -
05 2.4133: Use most efficient type of electric motors $816 $1,466 $699
12,603
kWh
$117
-
kW-mo/yr
- - - - - - - -
06 2.7135: Install occupancy sensors $640 $975 $611
11,430
kWh
$29
-
kW-mo/yr
- - - - - - - -
07 3.5217: Reuse / recycle/ sell paper products $2,969 $120 - - - $1,349
-
lb
- - - - $1,620 -
08 3.6192: Use a less expensive method of waste removal $384 $60 - - - $384
-
lb
- - - - - -
09 3.6192: Use a less expensive method of waste removal $8,160 $120 - - - $8,160
-
lb
- - - - - -
10 3.4156: Use flow control valves on equipment to optimize water use $5,595 $820 - - $5,595
-
Tgal
- - - - - - -
11 4.652: Replace existing equipment with more suitable substitutes $54,284 $180,000 - - - - $48,960 - - - - $5,324
12 4.812: Apply for investment incentives $1,580 $60 - - - - - $1,066 - $514 - -
TOTAL RECOMMENDED $88,803 $213,425 $14,913
288,393
kWh
$659
-
kW-mo/yr
$5,595
-
Tgal
$9,893
-
lb
$49,130 $1,066 $89 $514 $1,620 $5,324
TOTAL IMPLEMENTED $26,704 $31,570 $14,302
276,963
kWh
$630
-
kW-mo/yr
- $9,893
-
lb
$170 - $89 - $1,620 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings By-product Production Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs