ITAC Assessment: GT0113
ITAC logo
ITAC Assessment: GT0113
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product CONVEYOR BELT PARTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area
n/a
Annual Production 2,500
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $268,581 6,332,063
kWh
Natural Gas $161,009 42,211
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,824 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $1,711 $600 $1,711
40,445
kWh
-
02 2.4133: Use most efficient type of electric motors $1,811 $1,258 $1,811
42,790
kWh
-
03 2.2414: Use waste heat from hot flue gases to preheat $9,406 $50,000 - $9,406
-
MMBtu
04 2.7142: Utilize higher efficiency lamps and/or ballasts $11,896 $90,825 $11,896
280,481
kWh
-
TOTAL RECOMMENDED $24,824 $142,683 $15,418
363,716
kWh
$9,406
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs