Assessment Year | 2000 |
---|---|
Principal Product | Hardwood Mouldings |
NAICS |
n/a
|
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
198,000
ft2
|
Annual Production | 21,500
thousand feet
|
Production Hrs. Annual | 4,394
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $269,229 | 6,435,522 |
kWh
|
$0.042 |
Electricity Demand | $136,115 | 24,144 |
kW-mo/yr
|
$5.64 |
Electricity Fees | $1,285 | - |
|
- |
Natural Gas | $11,579 | 2,380 |
MMBtu
|
$4.87 |
LPG | $8,024 | 1,333 |
MMBtu
|
$6.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $62,184 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,695 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,974 | $251 |
$1,446
34,584
kWh
|
$528
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $1,511 | $500 |
$1,105
26,377
kWh
|
$406
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,561 | $21,339 |
$4,079
97,304
kWh
|
$1,482
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7135: Install occupancy sensors | $970 | $648 |
$970
23,154
kWh
|
- | - | - | - | - | |
05 | 2.3212: Optimize plant power factor | $2,134 | $1,750 | - | - | $2,134 | - | - | - | |
06 | 4.611: Begin a practice of predictive / preventative maintenance | $688 | - | - | - | - | - | $688 | - | |
07 | 4.652: Replace existing equipment with more suitable substitutes | $1,174 | $4,000 | - | - | - | - | $1,174 | - | |
08 | 4.652: Replace existing equipment with more suitable substitutes | $30,210 | $80,000 | - | - | - | - | $30,210 | - | |
09 | 3.5311: Recover and reuse waste material | $1,440 | $1,175 | - | - | - |
$1,440
-
lb
|
- | - | |
10 | 4.125: | $16,522 | $4,316 | - | - | - | - | - | $16,522 | |
TOTAL RECOMMENDED | $62,184 | $113,979 |
$7,600
181,419
kWh
|
$2,416
-
kW-mo/yr
|
$2,134 |
$1,440
-
lb
|
$32,072 | $16,522 | ||
TOTAL IMPLEMENTED | $33,695 | $80,751 |
$2,551
60,961
kWh
|
$934
-
kW-mo/yr
|
- | - | $30,210 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs