ITAC Assessment: DS0166
ITAC logo
ITAC Assessment: DS0166
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Hardwood Mouldings
NAICS
n/a
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 198,000
ft2
Annual Production 21,500
thousand feet
Production Hrs. Annual 4,394
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $269,229 6,435,522
kWh
Electricity Demand $136,115 24,144
kW-mo/yr
Electricity Fees $1,285 -
Natural Gas $11,579 2,380
MMBtu
LPG $8,024 1,333
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $62,184 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,695

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,974 $251 $1,446
34,584
kWh
$528
-
kW-mo/yr
- - - -
02 2.4221: Install compressor air intakes in coolest locations $1,511 $500 $1,105
26,377
kWh
$406
-
kW-mo/yr
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,561 $21,339 $4,079
97,304
kWh
$1,482
-
kW-mo/yr
- - - -
04 2.7135: Install occupancy sensors $970 $648 $970
23,154
kWh
- - - - -
05 2.3212: Optimize plant power factor $2,134 $1,750 - - $2,134 - - -
06 4.611: Begin a practice of predictive / preventative maintenance $688 - - - - - $688 -
07 4.652: Replace existing equipment with more suitable substitutes $1,174 $4,000 - - - - $1,174 -
08 4.652: Replace existing equipment with more suitable substitutes $30,210 $80,000 - - - - $30,210 -
09 3.5311: Recover and reuse waste material $1,440 $1,175 - - - $1,440
-
lb
- -
10 4.125: $16,522 $4,316 - - - - - $16,522
TOTAL RECOMMENDED $62,184 $113,979 $7,600
181,419
kWh
$2,416
-
kW-mo/yr
$2,134 $1,440
-
lb
$32,072 $16,522
TOTAL IMPLEMENTED $33,695 $80,751 $2,551
60,961
kWh
$934
-
kW-mo/yr
- - $30,210 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs