Assessment Year | 2000 |
---|---|
Principal Product | Circuit-boards and Wire Harnesses |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
36,360
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 4,368
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,931 | 799,238 |
kWh
|
$0.045 |
Electricity Demand | $20,135 | 2,580 |
kW-mo/yr
|
$7.80 |
Electricity Fees | $2,048 | - |
|
- |
Natural Gas | $3,114 | 600 |
MMBtu
|
$5.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,255 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,074 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $6,312 | $2,897 |
$4,026
134,232
kWh
|
- |
$2,286
-
MMBtu
|
- | - | - | - | |
02 | 2.7261: Install timers and/or thermostats | $763 | $1,113 | - | - |
$763
-
MMBtu
|
- | - | - | - | |
03 | 2.3137: Use power during off-peak periods | $1,067 | $900 |
$168
3,810
kWh
|
$899
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 3.8142: Distill contaminated solvents for reuse | $(-2,948.0) | $3,295 | - |
$(-309.0)
-
kW-mo/yr
|
- |
$801
-
gal
|
- | $(-650.0) | $(-2,790.0) | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,244 | $4,230 | - | - | - | - |
$1,244
-
lb
|
- | - | |
06 | 4.611: Begin a practice of predictive / preventative maintenance | $817 | - | - | - | - | - | - | $817 | - | |
TOTAL RECOMMENDED | $7,255 | $12,435 |
$4,194
138,042
kWh
|
$590
-
kW-mo/yr
|
$3,049
-
MMBtu
|
$801
-
gal
|
$1,244
-
lb
|
$167 | $(-2,790.0) | ||
TOTAL IMPLEMENTED | $3,074 | $6,243 |
$168
3,810
kWh
|
$899
-
kW-mo/yr
|
$763
-
MMBtu
|
- |
$1,244
-
lb
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs