| Assessment Year | 2000 |
|---|---|
| Principal Product | Fitness Equipment |
| NAICS |
n/a
|
| SIC | 3949: Sporting and Athletic Goods, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 340 |
| Plant Area |
200,000
ft2
|
| Annual Production | 62,920
pieces
|
| Production Hrs. Annual | 6,816
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $131,044 | 4,479,777 |
kWh
|
$0.029 |
| Electricity Demand | $112,326 | 10,272 |
kW-mo/yr
|
$10.94 |
| Electricity Fees | $7,547 | - |
|
- |
| Natural Gas | $61,034 | 21,044 |
MMBtu
|
$2.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,175 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,628 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $1,338 | $1,999 | - | - |
$1,338
-
MMBtu
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $630 | $216 |
$630
21,688
kWh
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,547 | $9,389 |
$2,144
73,857
kWh
|
$1,403
-
kW-mo/yr
|
- | - | - | |
| 04 | 4.812: Apply for investment incentives | $1,961 | $720 | - | - | - | - | $1,961 | |
| 05 | 4.611: Begin a practice of predictive / preventative maintenance | $293 | - | - | - | - | $293 | - | |
| 06 | 3.6125: Sell combustible waste | $4,406 | $900 | - | - | - | - | $4,406 | |
| TOTAL RECOMMENDED | $12,175 | $13,224 |
$2,774
95,545
kWh
|
$1,403
-
kW-mo/yr
|
$1,338
-
MMBtu
|
$293 | $6,367 | ||
| TOTAL IMPLEMENTED | $8,628 | $3,835 |
$630
21,688
kWh
|
- |
$1,338
-
MMBtu
|
$293 | $6,367 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs