Assessment Year | 1999 |
---|---|
Principal Product | Thermoset and Thermo-Plastic molding |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
68,124
ft2
|
Annual Production | 95,000,000
pieces
|
Production Hrs. Annual | 8,424
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $211,899 | 5,257,913 |
kWh
|
$0.040 |
Electricity Demand | $28,419 | 11,568 |
kW-mo/yr
|
$2.46 |
Electricity Fees | $7,571 | - |
|
- |
Natural Gas | $7,709 | 1,563 |
MMBtu
|
$4.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,971 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $862 | $319 |
$776
19,050
kWh
|
$86
-
kW-mo/yr
|
- | - | - | |
02 | 2.2437: Recover waste heat from equipment | $1,856 | $950 | - | - |
$1,856
-
MMBtu
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,335 | $383 |
$2,108
51,290
kWh
|
$227
-
kW-mo/yr
|
- | - | - | |
04 | 2.2511: Insulate bare equipment | $3,933 | $1,919 |
$3,933
95,838
kWh
|
- | - | - | - | |
05 | 3.5217: Reuse / recycle/ sell paper products | $7,000 | $400 | - | - | - |
$1,300
-
lb
|
$5,700 | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,781 | $4,480 | - | - | - |
$3,781
-
lb
|
- | |
07 | 4.441: Install automatic packing equipment | $10,104 | $3,000 | - | - | - | - | $10,104 | |
08 | 4.441: Install automatic packing equipment | $14,600 | $7,275 | - | - | - | - | $14,600 | |
09 | 4.211: Consider use / purchase of bulk materials where possible | $1,500 | $400 | - | - | - | - | $1,500 | |
TOTAL RECOMMENDED | $45,971 | $19,126 |
$6,817
166,178
kWh
|
$313
-
kW-mo/yr
|
$1,856
-
MMBtu
|
$5,081
-
lb
|
$31,904 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs