ITAC Assessment: DS0146
ITAC logo
ITAC Assessment: DS0146
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Sodium Hyaluronate
NAICS
n/a
SIC 2833: Medicinal Chemicals and Botanical Products
Sales Range $10
M
to 50
M
# of Employees 142
Plant Area 150,560
ft2
Annual Production 1,069
lb
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $176,191 6,184,056
kWh
Electricity Demand $107,530 13,260
kW-mo/yr
Electricity Fees $5,465 -
Natural Gas $76,578 25,323
MMBtu
Fuel Oil #6 $2,275 525
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,758 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,928

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.2414: Use waste heat from hot flue gases to preheat $1,610 $5,010 - - $1,610
-
MMBtu
- -
02 2.7135: Install occupancy sensors $440 $540 $440
15,240
kWh
- - - -
03 2.4221: Install compressor air intakes in coolest locations $561 $364 $366
12,603
kWh
$195
-
kW-mo/yr
- - -
04 2.2511: Insulate bare equipment $2,488 $856 - - $2,488
-
MMBtu
- -
05 2.2444: Use hot process fluids to preheat incoming process fluids $16,231 $8,361 $4,905
169,109
kWh
$4,379
-
kW-mo/yr
$6,947
-
MMBtu
- -
06 2.2444: Use hot process fluids to preheat incoming process fluids $1,235 $2,407 - - $1,235
-
MMBtu
- -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $1,185 $4,480 - - - $1,185
-
lb
-
08 4.131: Modify process to reduce material use/cost $3,008 $240 - - - - $3,008
TOTAL RECOMMENDED $26,758 $22,258 $5,711
196,952
kWh
$4,574
-
kW-mo/yr
$12,280
-
MMBtu
$1,185
-
lb
$3,008
TOTAL IMPLEMENTED $2,928 $1,396 $440
15,240
kWh
- $2,488
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs