ITAC Assessment: BD0339
ITAC logo
ITAC Assessment: BD0339
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Animal feeds
NAICS 311119: Other Animal Food Manufacturing
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $1
M
to 5
M
# of Employees 15
Plant Area 35,000
ft2
Annual Production 17,000
ton
Production Hrs. Annual 3,120
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,052 616,483
kWh
Natural Gas $30,292 5,500
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,340 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,965

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $83 $35 $66
916
kWh
- - $8 $9
02 2.7135: Install occupancy sensors $221 $75 $220
3,120
kWh
$1
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $55 $2 $54
774
kWh
$1
-
kW-mo/yr
- - -
04 2.4314: Use synthetic lubricant $116 $76 $115
1,635
kWh
$1
-
kW-mo/yr
- - -
05 2.1221: Replace obsolete burners with more efficient ones $10,344 $2,501 - - $10,344
-
MMBtu
- -
06 2.1222: Install turbulators $755 $781 - - $755
-
MMBtu
- -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $7,766 $9,021 $7,765
110,300
kWh
$1
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $19,340 $12,491 $8,220
116,745
kWh
$4
-
kW-mo/yr
$11,099
-
MMBtu
$8 $9
TOTAL IMPLEMENTED $7,965 $9,132 $7,946
112,851
kWh
$2
-
kW-mo/yr
- $8 $9
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs